An estimate is only useful if you can trust it, so this page lists exactly how our calculators turn your measurements into tons, cubic yards, gallons and dollars. Nothing is hidden in the code: every result on the site also shows a "How we got this" line with the numbers it used, and you can repeat any calculation by hand with the formulas below.

Our Principles

Asphalt Quantity

All asphalt calculators follow the same chain: area → volume → weight.

  1. Area. Rectangle = length × width. Circle = π × radius². Triangle = ½ × base × height. Multiple sections are added together.
  2. Volume. Area × compacted thickness. Thickness in inches is divided by 12 to get feet (or centimeters by 100 to get meters). Cubic feet ÷ 27 = cubic yards.
  3. Weight. Volume × density. In US units, pounds ÷ 2,000 = short tons. In metric, kilograms ÷ 1,000 = tonnes.
  4. Order quantity. Weight × (1 + waste %). The main calculator's Simple mode adds 5%; Advanced mode lets you choose.
  5. Truckloads. Order quantity ÷ truck capacity, rounded up. Default 20 tons, a typical legal load for a tri-axle dump truck.

Shortcut used on the site: tons = square feet × inches × 0.00604. This is 145 lb/ft³ ÷ 12 ÷ 2,000. In square yards it becomes about 110 lb per square yard per inch (145 × 0.75 = 108.75, conventionally rounded to 110).

On this page
  1. Our Principles
  2. Asphalt Quantity
  3. Default Values
  4. Why We Don't Add Compaction to Tonnage
  5. Cost Figures
  6. How We Check Results
  7. Corrections and Updates
  8. Sources

Default Values

Defaults used across the calculators (all editable)
ValueDefaultBasis
Hot mix asphalt, in-place density145 lb/ft³ (2,322 kg/m³)Midpoint of the Asphalt Institute's typical 142 to 148 lb/ft³
Spread rate110 lb/SY-inDensity × 0.75, common estimating convention
Warm mix / cold mix / porous143 / 130 / 125 lb/ft³Approximate planning values; confirm with your supplier
Waste allowance5%Common contractor practice of 5 to 10%
Roll-down (loose to compacted)25%Field rule of thumb of about 1/4 inch per inch; affects loose depth only
Crushed stone base1.5 tons per loose cubic yard, plus 25% for compactionTypical supplier figures range from about 1.35 to 1.7 t/yd³ loose; the 25% allowance follows common practice for dense-graded base
Truck capacity20 tonsTypical tri-axle legal payload of roughly 18 to 22 tons for hot mix
Ton / tonne2,000 lb / 1,000 kgNIST conversion tables

Specialized tools (sealcoat, cold patch, millings, gravel base) cite the coverage and density figures they use on their own pages.

Why We Don't Add Compaction to Tonnage

Some calculators add 15 to 25% to the tons "for compaction". That is a double count. Asphalt is bought by weight, and the density we use is the density after rolling. The paver lays the mix loose, roughly a quarter deeper than the finished mat, and the rollers squeeze the same tons into a thinner layer. So compaction changes the loose depth, which we report separately, but not the weight you order. Extra material for an uneven base, edges and spillage is real, and the waste allowance is where it belongs.

Loose granular materials such as crushed stone and millings are different: they are often sold by loose volume or loose weight, and they compact under a roller. Those calculators include a compaction allowance and explain it on the page.

Cost Figures

Cost tools multiply quantities by the unit prices you enter. Default prices and the ranges in our articles come from published US cost guides and supplier information that we review when we update a page; the review month is shown at the bottom of each page. Asphalt prices track crude oil and local demand and can move noticeably within a season, so always replace defaults with a current local quote.

How We Check Results